DCL Ltd specialises in all aspects of urban land development to do with residential subdivisions and industrial land division.
DCL take pride in completing all works from earth moving, sewer and storm water pipelines to roading giving a high level of finish that we are proud of and that the purchasers of the sections can be proud of.
Quality systems and Health and Safety allow for risk free completion to any clients high expectations.
Project |
Client/Purpose |
Aidenfield Subdivision Stage 7, 750 sections | KB Quarries Ltd, Sub Contractor |
Peninsula Bay Subdivision, Wanaka, 500 sections | CCC, Groynes Subdivision |
Ellington Estate Subdivision, 250 sections | Christchurch City Council |
Moorcroft Subdivision, 450 sections | Waimakariri District Council, Davis Ogilvie Consulting Engineers |
Forest Park Subdivision Stages Ten and Eleven, 350 sections | Christchurch City Council/Davie Lovell Smith Consulting Engineers |
Northwood Subdivision, 500 sections | Waimakariri District Council, Davis Ogilvie Consulting Engineers |
Sovereign Palms Subdivision, Kaiapoi, 600 sections | Suburban Estates Ltd/Davis Ogilvie Consulting Engineers |
The Groynes Park Subdivision, Christchurch, 650 sections |
September, 2016
Forming part of overall 93ha, 2000 residential lot, this work comprises a new 400 lot subdivision. Dormer’s work package involved the installation of major drainage services reticulation (sewer and stormwater gravity pipework), construction of new pump stations, finishing stormwater basins and wetlands, including storm water structure, pipework and the bulk Earthworks testing and commissioning. Work was undertaken concurrently with separate contractors for the roading and service installation.
Contract Statistics;
Environment |
Full compliance with regional and local authority requirements. |
Health and Safety |
Nil incidents |
Programme |
Work was staged to meet Separable Portions (to allow sequential release of key areas as work progressed). |
Cost/Budget |
Achieved |
September, 2016
Dormer Construction Ltd was given the contract to construct all the sewer and storm water pipelines and structures on the stages at the Peninsula Bay subdivision, Wanaka.
We also completed approximately 40,000 m3 of cut to fill operations during the earthworks period.
The Client ‘Infinity Investment Group’ – a Wanaka based company who specialise in land development projects throughout New Zealand were a pleasure to work for due to their professionalism and also their prompt payment.