LOCATION | Kaiapoi |
CLIENT | Waimakariri District Council | |
VALUE | $2.6 million | |
PROJECT START | June 2013 | |
COMPLETION | Jan 2014 |
Waimakariri communities were significantly affected by the earthquake and aftershocks that struck Canterbury in September 2010. This contract involved the reinstatement of infrastructure throughout the Kaiapoi District, replacing damaged sewers, sewer laterals, water reticulation and land restoration. Work was scheduled to meet separable portions at;
Environment |
Achieved compliance to Council and Environmental Canterbury environmental requirements. Traffic Management plans in place to reduce impact of works on traffic and pedestrian flows. |
Health and Safety |
Nil incidents |
Programme |
Separable portion programme prepared by Dormer Construction accepted by Council – achieved project milestones. |
Cost/Budget |
Value and measure. Worked collaboratively to identify opportunities to minimise cost. |