LOCATION | Christchurch City |
CLIENT | Fletcher Construction | |
VALUE | Approx $6.0million | |
PROJECT START | Jan 2012 | |
COMPLETION | On-going |
Dormer has completed a large number of projects awarded under the SCIRT alliance and continues to add projects to this portfolio of work. Typical scope of works includes all setting out of main pipeline (stormwater and sewer), temporary trenching, dewatering, cutting, excavation, penetrometer testing, lateral connections, junctions, trench and service support, haunching, associated manholes, backfilling, NDM compaction testing and restoration. In some cases Dormer were responsible for the construction, installation and commissioning and testing of pump/lift stations.
Overall approximately 4,000m of waste water piping ranging from 150mm to 375mm diameter and approximately 1000m of stormwater ranging from 285mm to 1800mmm (depth range 1.5m to 4m) , over 200 manholes and 10 lift stations has been installed by Dormer across Christchurch city. Significant projects include;
Chester and Durham St. $1.1M |
Montreal Street $1.1M |
Richardson Terrace $893K |
Crammer Square Lift Stn $245K |
PS7 Phase 2 & 3 Shirley $2.4M |
Environment |
Complied with SCIRT, Environment Canterbury and Christchurch Council requirement at all times for sediment control and methodology. |
Health and Safety |
SCIRT’s very high safety standards complied with without any significant incidents. |
Programme |
Achieved where works were not interrupted by extreme ground conditions, underground impediments. |
Cost/Budget |
Measure and value, approved variations. |