LOCATION | Johns Road - Christchurch |
CLIENT | Groynes Development 2012 | |
VALUE | $6 million | |
PROJECT START | January 2014 | |
COMPLETION | On going |
Forming part of overall 93ha, 2000 residential lot, this work comprises a new 400 lot subdivision. Dormer’s work package involved the installation of major drainage services reticulation (sewer and stormwater gravity pipework), construction of new pump stations, finishing stormwater basins and wetlands, including storm water structure, pipework and the bulk Earthworks testing and commissioning. Work was undertaken concurrently with separate contractors for the roading and service installation.
Contract Statistics;
Environment |
Full compliance with regional and local authority requirements. |
Health and Safety |
Nil incidents |
Programme |
Work was staged to meet Separable Portions (to allow sequential release of key areas as work progressed). |
Cost/Budget |
Achieved |